Ceramic application and continuation of other works
In this month of June, we highlight the continuation of the works of execution of the built-in infrastructures and the coverings of the facades of the building. Work continues on the application of window frames, false ceilings and interior partitions. This month also marked the beginning of the application of ceramic tiles.
Beginning of inner compartments

At River Plaza, the divisions of the apartments are now beginning to appear, through the interior compartmentation, and the different spaces of the house can now be seen – living room, kitchen, bedrooms, etc. Special installations are also ongoing.
The top of the building

River Plaza reached one of the most outstanding moments of its work – the completion of the structural work. This way, we’ve reach the top of the building, so we can see the shape of the building who asserts himself every day as the new icon of Gaia drawn over the landscape. At the same […]
Start of special installations

In January, special installations began, namely hydraulics and electricity. There was also the continuation of the masonry work and the structure, which is close to completion.
Start of masonry works

In the River Plaza project, the masonry work began, with the structure continuing to be developed at a good pace.
Work’s development

River Plaza’s structure work continues to be developed at a good pace.
Gaia: the latest luxury destination

Vila Nova de Gaia is the latest luxury destination in Porto, with the multiplication of five-star real estate and hotels. Since the beginning of the pandemic, at least five hotels with these characteristics have debuted and new openings are on the way. The breathtaking view of Porto weighs in on this onslaught, but it is […]
Continuation of the upper floors structure

In the River Plaza project, the ground floor slab was recently completed, and it is already possible to see the work froom the street. During the month of October, the concreting of the 1st floor slab is under development.
Beginning of the upper floors structure

In August, the structural work on the River Plaza building continued, with the beggining of the structure of the upper floors.
Execution of the building structure – Video

At the River Plaza project, the structural works are being developed, with the execution of pillars, slabs and beams. See the follow-up video by clicking on the image below.